Lots of dirt and rock must be moved to get to Arizona coal

Part two of a four-part series about the Black Mesa Mine, operated by Peabody Western
in Northern Arizona. A pdf version of the entire series, complete with photos and illustrations, is available here.

by Terry Ertter
Forget the stereotypes. Peabody Energy’s Black Mesa coal mine in Northern Arizona is nothing like the coal mines most of us have seen in the movies. At the Kayenta and Black Mesa mines, most of the miners spend their days operating wheel loaders, track-type tractors, draglines or other pieces of heavy equipment. The machinery does the dirty work.


As you can see from the photos of current mining operations, taking coal out of the ground, Arizona-style, requires some serious excavating. Before Peabody’s mining crews move in to begin working a section, reclaiming crews run a fleet of scrapers and track-type tractors at the site to pick up the topsoil and haul it away to be stockpiled for later. In most areas of Black Mesa, the soil goes down about four feet to rock. Once the soil is out of the way, mining crews come in, drill holes in the surface rock and blast it.


At this point, an incredibly large piece of equipment comes to the scene. The machine is called a dragline, and it’s sort of a cross between a crane and an excavator. The dragline house (the part with the engine and operating compartment) is roughly the size of a high school gymnasium, and the boom is about the length of a football field. Cables running up the boom from the housing are attached to a bucket with a capacity of 110 cubic yards! For comparison, Caterpillar’s largest shovel, the 5230B, has a bucket capacity of 21 cubic yards. The dragline, which retails for around $75 million, could easily snatch up a D11 or two and toss them aside.


The dragline’s job is to pick up a bucketful of shot rock, pivot 180 degrees and dump the load. When all the rubble has been moved from one side of the dragline to the other, crews come back with more explosives and blast another layer of rock to be moved. Eventually, the rock is cleared away to expose a seam of coal. If the seam is relatively shallow, a D10 or D11 can simply rip the coal and doze it into piles to be loaded by Cat 992 wheel loaders. Thicker seams call for more drilling and blasting.


All the blasting and earthmoving changes the terrain dramatically. On one side of the dragline, there’s a wide trench and a cliff of exposed rock and coal. The cliff is called the highwall. On the opposite side of the dragline are tall piles of waste rock referred to as spoil.


In the pit Tim May and I visited, the dragline was working in a horseshoe- shaped pattern around the coal deposit. After the dragline works its way around the horseshoe, the routine changes slightly. The first layer or two of shot rock now is dozed off the highwall into the trench. When the trench is filled to the same level as the ground the dragline rests on, the fill-rock is leveled and the dragline moves onto its new roadway. The dragline then works its way back around the horseshoe, piling new rock over its previous roadway.


When the dragline finally reaches the center of the horseshoe, and the coal is all removed, the dragline moves away to a new site. Peabody reclamation crews move back in with D11s and other earthmoving equipment to push the piles of spoil back to where the rock came from. They shape the spoil to match the surrounding, unmined terrain. The broken up rock is not packed as densely as when it was a solid slab, so the elevation is the same as before mining began even though the coal has been removed.


Once the contours are right, scrapers from either Skanska or Peabody haul the topsoil back and spread it to cover the rock. D9s massage the dirt into position and pack it down. When the dirt is in place and ready, crews come in to plant brush and grass to create hardy range land. A couple of years go by, and the site looks like it’s never been touched by a blade or a bucket.

Return to the main copywriting page

    
Return to the main writing page